Wednesday, January 2, 2013

55 Plaster

17.12.2012 : Monday

Turan Usta and his plaster crew start work: The first step is tying metal wire mesh ("rabis teli") to the wood laths. This is a lot of work. Then the crude first coat of lime-based plaster will come..


 
24.12.2012 : Monday
 
The plaster work starts...
 


 

54 Bedroom - Ceiling Beam - Ready for Ceiling Covering

15.12.2012 : Saturday

Levelling and adjustments to the sub-support frame on the ceiling are done, in preparation for the wood ceiling covering and ornamentation.

53 Embedding Loudspeakers

07.12.2012 : Friday

The topic of music: embedding loudspeakers in the walls, having an all-round music system in the house, wonderful ideas.. Discussions with Yüksel Bey from 'Activo', last minute electrical sound design before the plaster-phase starts.. The circular templates are put in place, and with the blue foam stuffed inside, we are all ready to plaster the walls!!




52 Detail - Window Frames

06.12.2012


51 Bedroom - Electricity

06.12.2012 : Thursday  -  08.12.2012 : Saturday

Electrical installations in the bedroom.

50 Living Room - Electricity

05.12.2012 : Wednesday  -  06.12.2012 : Thursday

Electrical installation work starts in the living room: İrfan Karadede and Mehmet Usta discuss the details..