13 Roof Terrace Structure

17.10.2012: Wednesday
 
In order to reduce the weight on the whole of the front façade, before starting structural work on the ground floor level, the dead weights on the roof terrace were lifted off. The wooden posts supporting the roof above the terrace, are rotten at their base. Thus, they are removed and a temporary construction is built so that the roof here is supported by the exterior scaffolding.


İsmail Usta from Esat Demirel's team is seen in the above pictures. He is very experienced.


Removal of the lead water drain pipes