33 Living Room - Interior Wall

12.11.2012 : Monday

Now that the timber-frame work of the interior living room wall is finished, the next step "çıtalama" has started: 1.5cm x 4cm wooden laths are mounted horizontally, first on the entrance hall side of the wall. This is in preparation of the special plaster that will be applied later. On the other side of the same wall, there is still some work to complete before the same steps are applied there as well. Rockwool will be placed inside for sound and heat insulation, as well as electrical installation.

Salih Usta is completing this task on his own...

 